A Guide to Flare, Relief, and Blowdown Systems - WittyWriter

A Guide to Flare, Relief, and Blowdown Systems

1. Purpose and Principles

The primary purpose of a flare, relief, or vent system is to provide a safe and controlled method for disposing of flammable, toxic, or hazardous materials from a process. These systems are the most critical safety layer for protecting equipment from overpressure and for managing emergency events.

A poorly designed flare system can constrain plant operability, create a new hazard, or fail to operate correctly during an emergency, potentially leading to catastrophic equipment failure.

This guide outlines the best practices for the design, sizing, and selection of these critical safety systems, based on common industry standards (such as API 520, 521, and ASME B31.3 & ASME VIII).

2. Components of a Typical Flare System

A flare system is comprised of four main parts that work together to safely handle a release:

  1. Flare System Sources: The individual devices that release fluid into the system. This includes Pressure Safety Valves (PSVs), rupture disks, automatic blowdown valves (BDVs), control valves (CVs), and drains.
  2. Gathering System: The network of pipes (laterals and the main header) that collects the fluids from all sources and transports them to a central disposal point.
  3. Knock-Out (KO) System: A vessel (or "KO Drum") that uses gravity to remove and collect any liquids from the vapor stream. This is critical, as flares are designed to burn vapor, and discharging burning liquids is a major hazard.
  4. Flare and Vent System: The final disposal device, typically a flare stack or vent, which releases the vapors to the environment. Flares combust the vapors, while vents release them uncombusted.

3. Basic Steps for Flare System Design

A flare system design follows a logical, step-by-step process to ensure all scenarios are captured and the system is sized correctly.

  1. Establish the Design Basis: Document all assumptions, standards, and governing philosophies.
  2. Identify Relief Scenarios: Identify all credible overpressure scenarios (e.g., fire, blocked outlet, power failure) for each piece of equipment.
  3. Calculate Relief Loads: Quantify the flow rate (kg/h) and properties for each individual relief case.
  4. Identify Blowdown Systems: Determine which systems require emergency depressuring (blowdown) for fire survivability.
  5. Calculate Blowdown Loads: Calculate the transient (time-based) flow rate for each blowdown case.
  6. Determine Coincident Loads: This is the most critical step. Analyze plant-wide failures (e.g., total power loss, cooling water failure) to find the combination of events that results in the maximum simultaneous flow to the flare. This "global" case typically sizes the main header, KO drum, and flare stack.
  7. Review System Segregation: Determine if any streams are incompatible and require their own dedicated flare system (see section 4.3).
  8. Size the KO System: Size the knock-out drum to handle the liquid from the worst-case scenario, typically providing 20-30 minutes of holdup time.
  9. Size Headers and Laterals:
    • Main Header: Sized by the governing "global" coincident load.
    • Laterals/Tailpipes: Sized by their own "individual" load, which is often a different, more severe case for that specific pipe.
  10. Perform Hydraulic Analysis: Model the flare network to confirm backpressures, velocities, and acoustic/flow-induced vibration risks.
  11. Perform Radiation & Dispersion Analysis: Set the flare stack height and location to ensure thermal radiation and gas dispersion (in a flame-out) are within safe limits for personnel and equipment.
  12. Perform Low-Temperature Study: Check for low temperatures from Joule-Thomson (J-T) cooling, especially in blowdown lines, to select correct materials and prevent brittle fracture.
  13. Document Everything: Create a comprehensive flare system design basis document that can be referenced for the life of the plant.

4. Defining the Design Loads

4.1 Pressure Relief (PSV) Loads

These are calculated based on specific overpressure scenarios as defined by API 521. Inlet and outlet lines for a PSV must be designed for the rated capacity of the valve, not just the calculated relief load.

4.2 Blowdown (BDV) Loads

Blowdown systems are designed to depressure equipment during a fire, reducing internal pressure as the vessel heats up to prevent rupture. The required rate is based on vessel survivability, with a common empirical guideline being to depressure the vessel to 50% of its design pressure within 15 minutes.

4.3 Coincident Loads (The Governing Case)

Critical Design Principle: The flare header and stack are almost never sized for a single event. The governing case is the maximum coincident load, which is the sum of all individual relief and blowdown events that can happen simultaneously due to a single cause.

Typical plant-wide coincident scenarios to analyze include:

4.4 Segregation of Flare Streams

It is often unsafe or impractical to combine all streams into a single header. Separate flare systems (e.g., an HP flare and an LP flare) may be required. Segregation is necessary to prevent:

5. Advanced Flare Design Strategies

5.1 High-Integrity Protection Systems (HIPS)

A HIPS is an instrumented system (e.g., sensors, logic solver, and valves) designed to be reliable enough to prevent an overpressure event from happening in the first place. By using a certified HIPS, a specific relief scenario can sometimes be eliminated, reducing the required size of the flare system. This is an advanced, high-cost solution that requires rigorous lifetime testing and management.

5.2 Staggered Blowdowns

Blowdown loads are characterized by a very high initial flow that quickly tapers off. Instead of sizing the flare for the massive, instantaneous peak of all systems blowing down at once, an instrumented system can be used to "stagger" the sequence. For example:

This reduces the peak flowrate and can significantly reduce the required flare header size. This approach is common in brownfield projects to add new equipment to an existing, constrained flare system.

6. Construction and Physical Design

6.1 Line Sizing and Inlet Pressure Drop (Ξ”P)

Proper line sizing is critical for PSV stability. If the pressure drop in the inlet piping to a PSV is too high, the valve will "chatter" (open and close rapidly), destroying itself and failing to protect the vessel.

Critical Design Rule: The total non-recoverable pressure loss in the inlet piping to a spring-loaded PSV must be less than 3% of the valve's set pressure. This calculation must be performed at the valve's rated capacity.

6.2 Wall Thickness: Beyond Pressure

The wall thickness of flare piping is often governed by mechanical integrity, not just pressure containment. A thicker wall is required to resist vibration-induced fatigue.

Best Practice: Flare system piping should be a minimum of Schedule 40/40S unless a specific engineering analysis for AIV and FIV has been performed and approved.

6.3 Material Selection: Extreme Temperatures

Flare systems must be designed for both high and low-temperature excursions.

7. Relief Device Selection and Installation

7.1 Relief Valve (PSV) Selection

The choice between Conventional, Balanced, or Pilot-operated PSVs is critical and depends on the service and, most importantly, the backpressure.

PSV Selection by Backpressure

Total Backpressure (% of Set Pressure) Acceptable PSV Type
≀ 10% Conventional, Balanced, or Pilot
≀ 30% Balanced or Pilot
≀ 50% Pilot-Operated

PSV Selection by Service

Selection Logic:

  1. Is the fluid Liquid or Two-Phase?
    • β†’ Use a Conventional or Balanced valve.
  2. Is the fluid Gas/Vapor?
    • Is the service "Dirty"? (e.g., wet gas, hydrates, solids, wax)
      • β†’ Use a Conventional or Balanced valve. (Pilots will plug).
    • Is the service "Clean"? (e.g., dry gas)
      • Is it a small, low-pressure valve?
        • β†’ Use a Conventional or Balanced valve (more economical).
      • Is it a large, high-pressure, or high-capacity valve?
        • β†’ Use a Pilot-Operated valve (lighter, more stable, better seat tightness).

7.2 PSV Sparing Philosophy

The decision to install a spare PSV depends on the criticality of the equipment it protects.

Interlocks: When an installed spare is used, the upstream and downstream isolation valves must be mechanically interlocked to ensure that it is impossible to isolate both the duty and the spare PSV at the same time.

7.3 Rupture Disks (Bursting Disks)

Rupture disks are non-reclosing devices that burst at a specific pressure. They are generally not preferred because they empty the entire system inventory, but they are used in specific cases:

When a rupture disk is installed upstream of a PSV, the PSV's capacity must be de-rated by a factor of 0.9. A pressure gauge must be installed in the space between the disk and the PSV to detect leaks.

8. Disposal System: Flares and Vents

The final disposal system is chosen based on environmental, safety, and economic considerations.

8.1 Atmospheric Vents

Vents release uncombusted gas to the atmosphere. They are only used for low-flow, near-atmospheric pressure streams where the gas is non-toxic and environmental impact is minimal. They must be continuously purged to prevent air from entering the pipe, which could create an explosive mixture. Dispersion analysis is required to ensure gas does not reach grade or ignition sources.

8.2 Flare Types

Flares are used to combust waste gas, converting it to COβ‚‚ and water. The type of flare is chosen based on capacity, cost, and public visibility.

Flare Type Advantages Disadvantages
Elevated Flare (Pipe) β€’ Low capital cost
β€’ Simple design
β€’ Best gas dispersion
β€’ High flame visibility
β€’ High noise levels
β€’ High thermal radiation at grade
Enclosed Ground Flare β€’ No flame visibility
β€’ Low noise
β€’ Small plot space
β€’ Highest capital cost (refractory-lined)
β€’ Capacity limited by enclosure size
β€’ Enclosure is still highly visible
Ground Pit Flare β€’ Median cost
β€’ Reduced visibility (flame is in a pit)
β€’ Noise is shielded by pit walls
β€’ Requires a large plot space
β€’ Complex staging and valving
β€’ Can be a confined space risk
Horizontal Pit Flare β€’ Lowest capital cost
β€’ Simple design
β€’ Good for liquid carryover
β€’ High noise levels
β€’ Requires large plot space
β€’ Contaminants directed horizontally
πŸͺ We use cookies to improve your experience. Learn more